Monday and Tuesday (1/14 and 1/15) are off. There wasn't enough interest, and I must admit, I do want to study for my finals.
Start selling cookies! (Assuming, of course, that you haven't already started)
What we did
1) Schedule robot season until Feb 1. (attached)
2)
Set up white boards upstairs with the schedule. One has the calendar
and the other has a detailed list of what needs to be done the next few
days
2) Prototyped claws (some more)
3) Marketing meeting - showed off the slide show, and got an update on the websites progress
What's for the weekend?
Mechanical (finish by 1/13): Machine chassis parts
Mechanical (finish by 1/13): Design elevator
Mechanical (finish by 1/13): Make Battery Box? (If we want it welded, we should send it to the welder at the same time the chassis is being welded.)
Mechanical: Design claw
Electronics (finish by 1/13): Make OI board
(The white board upstairs has an even more detailed schedule for the weekend. Check it to see what needs to be done.)
For those of you that just want a list of deadlines ... here it is!
Jan 13: Elevator designed
Chassis ready for welder
Jan 15: Chassis Welded
Jan 18: Rolling chassis completed
Jan 20: Claw design done and reviewed
Jan 21: Transmission on robot
Jan 22: OI finished
Jan 23: Electronics laid out
Finish cutting pieces for
elevator and claw
Jan 25: Elevator welded
Jan 28: Elevator working
Claw working
Jan 29: Electronics finished
Feb 1: Finished Robot!
--Katherine
Comments